dc.description.abstract | The second year workplan was approved in December, 2002. Despite the holiday season
and national elections, project activities still continued during the quarter. Follow-up
investigations of the suspected Laikipia rinderpest outbreak were finalised. The project
technical assistant was recruited by AU/IBAR and reported in January, 2003.
Update: Due to delay in receiving year 2 funds in time, it has become necessary to revise
the project's activity time chart. See the attached Annex H for details.
Further, it has been noticed that the Year 2 project financing document contains some
errors that need to be corrected. For this reason, together with the need to revise the