dc.description.abstractThe second year workplan was approved in December, 2002. Despite the holiday season and national elections, project activities still continued during the quarter. Follow-up investigations of the suspected Laikipia rinderpest outbreak were finalised. The project technical assistant was recruited by AU/IBAR and reported in January, 2003. Update: Due to delay in receiving year 2 funds in time, it has become necessary to revise the project's activity time chart. See the attached Annex H for details. Further, it has been noticed that the Year 2 project financing document contains some errors that need to be corrected. For this reason, together with the need to revise the activity time chart, an addendum is under preparation.
dc.subjectPan-African Control of Epizootics (PACE)
dc.titlePACE Kenya project first quarter progress report for year 2 annual work programme.
dc.typeReport


Files in this item

Thumbnail

This item appears in the following Collection(s)

Show simple item record